⚡ TRIAL VERSION — Save 3 projects · Reports print with watermark
| 🔥 Launch Price: Pro ₱999 · Business ₱1,999
| 👥 0/100 licenses claimed
| Download Now →
Load Audit — Appliance Energy & Peak Demand Calculator
ℹ
Fill in your appliances below. The audit calculates: daily kWh, peak running load (kW), and — critically — the surge/inrush peak that must not exceed your inverter's surge rating. Motor loads (AC, pumps, fridge) have high startup current. Click "Apply to Design Inputs" to transfer the results automatically.
When done →
Appliance / Load
Watts (W) Nameplate
Qty
Day hrs
Night hrs
kWh/day w/ DF
Load Type NEC/IEC 61000-3-2
Demand Factor %
Duty % Cycle
PF Power factor
VA Apparent pwr
Inrush × Mult.
Surge W No DF
Daily Energy Summary
Total Daytime Load
0.00
kWh/day
Total Nighttime Load
0.00
kWh/day
Total Daily kWh
0.00
kWh/day
Avg Monthly Bill Est.
₱0
Peak Demand & Inverter Sizing
Running Peak (kW)
0.00
kW
Sum of all loads running at the same time, with demand factor applied. = Σ (W × qty × duty% × demand factor) — drives inverter continuous rating.
Surge Peak (kW)
0.00
kW
Worst-case millisecond spike when the largest motor starts while everything else is already running. = Running peak + (Motor inrush W − Motor base running W) e.g. All loads running (4.12 kW) + Water Pump inrush (2.24 kW) − Pump base (0.19 kW) = 6.17 kW surge
Recommended Inverter
0.00
kW continuous
Minimum continuous rating with 20% safety headroom (NEC 220.97). = Running peak kW ÷ 0.80 The inverter's surge rating (2.5–3× continuous for LF type) must also exceed the Surge Peak above.
Largest Single Motor Surge
—
= Nameplate W × Qty × Inrush multiplier
This single load drives the surge peak calculation.
📐 Surge Peak Calculation Breakdown
⚠
Load Classification Guide — NEC Art.220, NEC Art.430, IEC 61000-3-2, IEEE 141
✓ Resistive — 1.0×
PF = 1.0 | No harmonics | No surge
Incandescent bulbs, heating elements, rice cooker, electric stove, water heater, electric iron (steady-state).
⚡ Electronic — 2.0×
PF = 0.85 | THD 10–150% | Inrush 1.5–2×
LED drivers, laptops, TVs, phone chargers, routers, SMPS. Non-linear per IEC 61000-3-2. NOT resistive. Demand factor auto-applies for qty ≥5.
⚠ Light Motor — 3.0×
PF = 0.80 | NEC 430.24: 125% FLA
Ceiling fans, stand fans, washing machines, blenders, power tools. Inrush 2–4×. DF 75% if qty ≥4 (NEC 220.53).
🚨 Heavy Motor — 6.0×
PF = 0.75 | Inrush 4–8× DOL
AC units, ref compressors, water pumps, deep-well pumps, air compressors. DF 65% if qty ≥4 (IEEE 141). Use soft-starter to reduce to 2–3×.
⏱ Short-Duration — 1.0×
PF = 1.0 | NEC 220.60: 50% DF
Loads used <30 min at a time: microwave, kettle, hair dryer, toaster. 50% demand factor for energy; 100% for surge check.
💡Key insight: LED lights are not resistive — they use switching driver circuits (non-linear loads per IEC 61000-3-2 Class C). TV sets, laptop chargers, phone chargers, and routers are all electronic non-linear loads. Demand Factor is automatically applied per NEC/IEEE: 10 LEDs at 100% DF vs. 20+ LEDs at 50% DF — because not all rooms are occupied simultaneously. The VA column (not W) is what your inverter must actually supply.
Project Information
SINGLE PHASE — Residential / Small Commercial
Saved Projects
Cable Run Distances — Voltage Drop
Array → Inverter (one-way, meters)
Inverter → Panel Board (one-way, meters)
Daily Load Profile & Battery Autonomy
Energy used during solar hours (~6am–6pm)
Energy used at night — supplied by battery
Battery Sizing Scenario
Lights, fans, fridge, router — essential loads only
Battery = MAX(night kWh, backup kW × hrs) — not the sum
🌀
Extended Autonomy Mode — Typhoon / Extended Cloudy Period No solar for N days. Battery supplies critical loads continuously (24h/day) — fridge, router, lights, fans, phone chargers. These run non-stop during the outage, so battery = criticalKw × 24h × N days. Leave blank to default to 50% of your average daily power draw.
Lights + fans + fridge + router — runs 24h continuously during typhoon. Blank = 50% of average total daily power.
⚠No critical load specified — using 50% of average total daily power as default (— kW). This load runs continuously 24h during typhoon. Enter your actual critical load for accurate battery sizing.
Estimated Battery Requirement
Critical load
—
× 24hrs/day
—
× Autonomy days
—
= Battery needed
—
Peak Surge Demand — Inverter Sizing
All loads ON simultaneously — drives inverter continuous rating
Inrush when largest motor starts — inverter surge rating must exceed this
Surge Check — Selected Inverter
Select inverter in Equipment tab
Surge rating vs. demand
—
💡LF (Low Frequency) inverters surge at 2–3× continuous — better for motor loads. HF inverters: only 1.5–2×. Always choose LF for systems with AC units or pumps.
System Parameters
80.0%
Loss Components
Wiring & Cable
2.0%
Inverter Conv.
4.0%
Soiling & Dust
3.0%
Module Mismatch
2.0%
Shading
1.0%
Temperature derating handled separately by Tc Pmax + mount type above.
Recommended: 90–95% of inverter max VDC
0.50%/yr
0.20% — Premium TOPCon0.55% — Standard PERC1.0% — Old/Budget
Monthly Savings vs. Monthly Amortization — The Key Question
ℹRun the calculator and adjust financing above to see your monthly comparison.
Full Financing Comparison — All Terms
Term
Down Payment
Loan Amount
Monthly Amort.
Monthly Savings
Monthly Net
Total Interest
Payback
Project Cost Breakdown
Solar Panels —
Inverter / Hybrid Inverter —
Battery Bank —
Racking & Mounting—
Wiring & Protection—
Installation Labor—
Permits & Misc—
Total Project Cost—
Battery Mode Comparison — Cost & Export Impact
How your system cost and export behavior change across the three battery sizing modes. Export happens when the array generates more than daytime load + battery charge needs — the surplus feeds back to the grid.
Run the calculator to see mode comparison.
Environmental Benefits
Annual Energy Generated—
Annual CO₂ Offset—
Equivalent Trees Planted—
25-Year Investment Returns
Monthly Savings (avg)—
Annual Savings (Year 1)—
Simple Payback (cash)—
NPV (25 Years)—
IRR (25 Years)—
25-Year Total Savings—
25-Year Net Profit—
💡Solar vs. Bank Deposit: Even at 7% IRR, solar significantly outperforms a bank time deposit (~5% p.a.) — and your savings grow every year as electricity rates rise.
🔌 Net Metering — Export Excess Energy to the Grid
Earn credits from your electric company for unused solar energy you send back to the grid.
Monthly Bill Credit
—
Remaining Bill
—
Bill Reduction
—
🔌
Run the calculator first, then come back here to explore net metering.
⚠Off-Grid Inverter Selected: Your selected inverter () is an off-grid type and cannot connect to the grid — net metering is not possible with this inverter. To use net metering, switch to a Grid-Tie or Hybrid Grid-Tie inverter (e.g. Growatt SPH, Deye SUN-15K, Huawei SUN2000, SolaX X1-Hybrid, Sungrow SH, SMA Sunny Boy, Fronius Primo).
Net Metering Settings
⚠ NORDECO Transition: Currently ₱12.90/kWh (Tagum, Nov 2025). DLPC authorized takeover under RA 12144 — SC upheld Jan 2026. Solar ROI is higher at current NORDECO rates. If DLPC takes over, use ₱10.50/kWh or Custom rate.
Export Rate
—
₱ per kWh exported
Daily Energy Balance — Where Does Your Solar Energy Go?
☀ Solar Generated
—
kWh/day
🏠 Used Daytime
—
kWh/day
🔋 Charges Battery
—
kWh/day
⚡ Exported to Grid
—
kWh/day
🌙 Night from Battery
—
kWh/day
Export Earnings
Energy Exported Daily—
Energy Exported Monthly—
Energy Exported Yearly—
Export Rate (₱/kWh — generation credit)—
Monthly Bill Credit (export)—
Annual Bill Credit (export)—
Estimated Remaining Monthly Bill—
⚠ Fixed charges (₱900/mo) cannot be offset by NM credits — this is your minimum bill regardless of system size.
Impact on Your Bill & Investment
Monthly Savings (self-consumption)—
Monthly Bill Credit (NM export)—
Estimated Remaining Bill—
Bill Reduction—
Payback Period—
25-yr Net Profit—
⚠Net metering requires a grid-connected inverter. Your current selection is off-grid only.
System Comparison — NM Optimized vs Full Self-Consumption
How Net Metering Helps Cover Your Monthly Loan Payment
Philippine Net Metering — What You Need to Know
📋 Legal Basis
Governed by ERC Order No. 2009-12-0013-SC and Republic Act 9513 (Renewable Energy Act of 2008). All distribution utilities are mandated to accept net metering applications.
⚡ System Size Limit
Net metering is available for systems up to 100 kW — covers virtually all residential and small commercial systems.
💡 How Credits Work
Excess energy exported is credited at the blended generation charge of your utility. Credits appear on your monthly bill and reduce what you owe. If credits exceed your bill, the surplus rolls over to next month.
🔧 What You Need
A grid-tie or hybrid inverter, a bi-directional meter (installed by your utility), and a net metering agreement with your distribution utility.
ℹSelect specific brands and models. The calculator validates string voltages against the selected inverter. Click Apply & Recalculate after choosing.
Solar Panels
Technology—
Wattage—
Voc / Vmp—
Efficiency—
Unit Price—
Inverter / Hybrid
AC Rating—
Type—
Max PV VDC—
MPPT Range—
Price—
Battery
Chemistry—
Capacity—
Cycle Life—
Warranty—
Price/Unit—
📄
Run the calculator to generate the report.
🏷 Your Details on Quotation (replaces "Checkway Electrotech PH" on client copy)
⭐ Pro: your name, phone & address appears on the quotation header — Checkway branding is removed. 🏢 Business: add your company logo on top of that.
💰 Markup / Selling Price
Set your profit margin per line item. Client sees selling price — cost is never shown.
% global
☀ Solar Panels
%—
⚡ Inverter
%—
🔋 Battery Bank
%—
🔩 Racking & Cabling
%—
🔧 Labor & Commissioning
%—
📋 Permits & Misc
%—
Your Cost
—
Client Price
—
Gross Profit
—
Gross Margin
—
🔒 Cost prices never appear on client quotation
📝 Terms & Conditions (printed on quotation — edit to match your business)
days from date of quotation
🔐
Admin Access
This section is for Checkway Electrotech staff only. Enter your admin password to manage the equipment database and view formulas.
Incorrect password. Please try again.
✓Admin mode active — Checkway Electrotech equipment database management panel.
🧪Tier Test Mode
Switch license tier to test how the calculator behaves for each tier. Reloads the page to apply. Settings are for this browser session only — does not affect the actual license file.
Current: trial
Lead Gate:checking…— clears captured flag so email form shows again on next Calculate
🏢 Business Branding — Test Configuration
This simulates what a Business licensee sees after running the Personalizer tool. Check quotation printout, report header, and watermark removal.
#
Brand
Model
Tech
Wp
Voc
Vmp
Isc
Tc Voc
Price ₱
Actions
#
Brand
Model
Type
kW
Max VDC
MPPT V
MPPTs
Price ₱
Actions
#
Brand
Model
Chem
Ah
V
kWh
DoD%
Cycles
Warranty
Price ₱
Actions
Engineering Formulas — Admin Reference (Not visible to customers)
✓Validated against NEC Article 690, IEEE 1562, and Mayfield Renewables engineering standards.
1. PV Array Sizing (Combined Method)
// Battery energy needed — depends on selected modeE_battery = MAX(Night_kWh, Backup_kW×Hrs) // Mode: Night+BackupE_battery = (Day_kWh + Night_kWh) × Days // Mode: Extended Autonomy// PV must also recharge the battery each day:Battery_charge_kWh = E_battery / Batt_RT_eff
// Total array daily output required (IEEE 1562 combined method)Total_array_kWh = Day_kWh + Battery_charge_kWh
// Temperature derating — cell temp rises above ambient in PH heatT_cell = T_ambient(35°C) + Mount_adder(25–35°C)
P_derate = 1 + (Tc_Pmax/100) × (T_cell − 25) // < 1.0 in hot climate// Required kWp — array must be LARGER to compensate for heat lossRequired_kWp = Total_array_kWh / (PSH × η × P_derate)
2. NEC 690.7(A) Cold-Temp Voc Check
// Per NEC 690.7(A)(1) — Tc method (accurate)CorrFactor = 1 + (Tc_Voc/100) × (T_cold − 25)
Voc_cold_per_panel = Voc_STC × CorrFactor
String_Voc_cold = N_panels × Voc_cold_per_panel
// MUST be ≤ Inverter_Max_VDC × safety_marginMax_panels = FLOOR(Inv_Vmax × margin / Voc_cold)
3. Battery Bank Sizing — Three Modes (IEEE 1013 / IEEE 1562)
// MODE 1: Night Only (grid-tied, daily cycling)E_battery = Night_kWh
// MODE 2: Night + Backup (hybrid/off-grid)// Backup runs from SAME battery — size for the LARGER scenario:E_battery = MAX(Night_kWh, Backup_kW × Backup_hrs)
// MODE 3: Extended Autonomy — Typhoon/Bad Weather (IEEE 1562 §5.3)// No solar for N days. Battery supplies ALL loads — day AND night:E_battery = (Day_kWh + Night_kWh) × Days_of_Autonomy
// Philippines typical: 2 days for standard, 3 days for critical// Ah sizing (all modes) — IEEE 1013 formula:Required_Ah = (E_battery × 1000) / (sysV × DoD × Inv_disch_eff)
// Inv_disch_eff ≈ 0.93 (DC→AC conversion loss from battery)Bank_config: blocks_series = sysV / block_V
strings_parallel = CEIL(Required_Ah / block_Ah)